Your Rights When Authorities Fail to Decide on Time
November 12, 2026Author: Dana Kweekel

When the Government Goes Silent: Your Rights When Authorities Fail to Decide on Time
By Dana Kweekel | BZSE law | November 2026
You filed an application months ago — perhaps for a business permit, a concession, a building license, or a residency permit. The deadline has passed, emails go unanswered, and you are told to "be patient". What are your rights when the government does not decide within the applicable timeframe?
In Sint Maarten, administrative bodies such as the government or SZV regularly face delays in deciding on applications and objections. The reasons may include staff shortages, incomplete policy, pending studies, or internal reorganization. But recent case law makes one point clear: internal administrative problems do not remove the government's legal obligation to decide.
This article explains what happens when the government does not decide on time, what the courts have said about governmental delay, and which remedies are available to applicants.
The law
Administrative law in Sint Maarten is governed by the Landsverordening administratieve rechtspraak (National Ordinance on Administrative Law / "LAR"). Article 3, paragraph 3, provides the starting point:
"Where the statutory period for issuing a decision has expired without a decision being given, or — in the absence of such a period — where a decision has not been given within a reasonable time, this is deemed a refusal to give a decision."
In other words, where the applicable deadline has passed without a decision, the law treats the silence as a refusal to decide. That gives the applicant access to the legal remedies available against this refusal.
For decisions on objections (beslissingen op bezwaar), the statutory period is four months. This period may be extended once by thirty days, provided that prior notice is given.
For primary applications, such as permits, concessions and licenses, the applicable period may be set by sector-specific legislation. If no specific period applies, the authority must decide within a reasonable time. Courts have generally regarded around three months as a useful benchmark for straightforward matters, while more complex applications may require more time.
What the courts have said
Recent decisions of the Joint Court of Justice and the Courts of First Instance in the Dutch Caribbean show a consistent approach: administrative difficulties do not, by themselves, justify missing a statutory or reasonable decision deadline.
"We don't have enough staff." A 2026 Sint Maarten case illustrates this point. The Minister explained that a high workload and capacity shortages at the Legal Affairs department had prevented the processing of an objection filed eight months earlier. The Court nevertheless held that "capacity shortages do not relieve the respondent of its obligation to decide on the objection in time". The objection had not been processed during the statutory period.
"We need to develop policy first." The same approach was taken in the Otium case of 10 June 2026 , concerning an electricity production concession in Curaçao. The Minister argued that he first needed to develop an allocation mechanism and complete technical studies. The Court found that the Minister had essentially waited for an external consultant’s report and held that this passive approach had caused the court-ordered deadline to be missed.
"The legally required advisory committee doesn't exist." In a 2025 Bonaire pharmacy permit case , the Minister argued that he could not decide because the statutory advisory committee had not been established. The Court held that the absence of the committee did not relieve the Minister of his obligation to decide in time. If necessary, the Minister should have found another way to obtain the required expert advice.
"We're waiting for advice from another department." A 2026 Curaçao building permit case concerned a delay of more than two years while the Minister waited for an assessment from the fire department. The Court held that waiting for advice from another department did not relieve the Minister of the duty to monitor the decision deadline and decide in time. The Court emphasized the applicant’s interest in knowing where she stands within a reasonable period.
The "pokopoko" principle
The strict approach to decision deadlines may raise questions about the so-called pokopoko principle in Dutch Caribbean jurisprudence. Those questions deserve a careful answer, because the principle does not merely fail to support governmental delay — its underlying rationale directly confirms the opposite.
The term comes from Papiamento and means "little by little" or "slowly." The principle was first articulated by the Joint Court of Justice in 2001 and confirmed by the Dutch Supreme Court in Erven R./Sint Eustatius. That case concerned a decades-long series of assurances by functionaries of the Island Territory of Sint Eustatius about the transfer of a plot of land, made by an organ that lacked formal authority to bind the territory. When the territory ultimately refused to proceed, the heirs of the original claimant sought damages for breach of trust. The central question was how much legal weight could be attached to that informal conduct.
The Supreme Court's answer was grounded in the nature of small-island administration. It held that, in a small-scale community where personal relationships are important and an explicit refusal may not easily be given, the rules governing authority and formal decision-making must be strictly observed. This principle carries significant weight, even though the Court also held that, in exceptional circumstances, even unauthorized conduct can give rise to liability. The principle therefore defines the starting point: formal procedures must be followed, precisely because informal dealings are more likely and more dangerous in close-knit communities.
The Supreme Court confirmed this reasoning in October 2024 in Shipyard/Sint Maarten, where Shipyard argued that a building permit issued by the Minister of VROMI implied the government's private-law consent to deviate from the terms of its ground lease. The Court rejected that argument. Critically, it also set out the reason why formal procedures carry particular weight in this context: public administration on Sint Maarten is, as a rule, less well-staffed and equipped for all its tasks than in European Netherlands, and it is precisely for that reason that strict compliance with procedures is of great importance, to safeguard the interests of the territory and its population.
It might be argued that the same circumstances — limited administrative capacity and the small-island context — should lead courts to allow more time before a deemed refusal arises. The pokopoko principle, on this reading, would reflect a broader recognition that formal legal standards must accommodate local realities.
The case law does not support that argument. The pokopoko principle was developed in response to the risk of informal conduct in small communities, and the Supreme Court has been explicit that limited resources are a reason to insist on formal procedures, not to relax them. That conclusion follows directly from the principle's own logic: it concerns situations where a citizen relies on informal or unauthorized governmental conduct, whereas a decision deadline involves a citizen asking the government to comply with a statutory obligation it assumed when it accepted the request. Invoking the pokopoko principle to argue for more time would turn its rationale on its head.
The courts have therefore consistently emphasized legal certainty. Applicants must be able to know when a government decision can be expected and what legal options are available if it does not come. The particular circumstances of small-island administrations may be relevant in some areas of administrative law, but — as the Supreme Court has made clear — those circumstances make enforceable deadlines more, not less, important.
What you can do
The LAR provides several remedies when an authority does not decide on time. The appropriate step depends on the circumstances and on whether the authority has already been ordered by a court to decide.
Step 1 — Appeal against the deemed refusal. Once the applicable deadline has expired, an applicant can file an appeal (beroep instellen) with the Court of First Instance. The appeal period is six weeks from the date on which the decision is deemed to have been refused. An appeal filed too early or after the six-week period may be declared inadmissible.
tep 2 — The court orders the authority to decide. If the appeal is well-founded, the court can order the authority to issue a decision within a specified period. The period may vary depending on the nature and complexity of the matter.
Step 3 — Penalty payments for non-compliance. If the authority does not comply with the court’s order, the court may attach a penalty payment (dwangsom) under Articles 50 or 97/98 LAR. In the Otium electricity concession case, the Joint Court imposed a lump-sum penalty of Cg 1,000,000 for failure to meet the January 2027 deadline.
Step 4 — The court may decide itself. Article 50 LAR allows the court, in appropriate circumstances, to substitute its own decision for that of the authority. In a 2026 Curaçao building permit case, the Court concluded that the long passage of time and the Minister’s lack of decisiveness gave it insufficient confidence that the Minister would comply with another order. The Court therefore ordered the Minister to grant the building permit.
Step 5 — Damages. The Joint Court may award non-pecuniary damages for unreasonable procedural delay under Article 6 of the European Convention on Human Rights. The current rate referred to in the case law is Cg. 500 per half-year of delay. Material damages, such as lost income or missed opportunities, may be pursued separately where the legal requirements for such a claim are met.
Practical guidance
Keep track of your deadlines. Record when your application or objection was filed, which statutory or reasonable decision period applies, and when the decision is deemed to have been refused. These dates determine when legal remedies become available.
Do not act too early, but do not wait indefinitely. An appeal filed before the reasonable decision period has expired will be inadmissible. For straightforward matters, three months is a useful benchmark. More complex applications may justify a longer period, but the authority should be actively dealing with the application rather than simply allowing it to remain pending.
Put the authority on notice. Although a formal ingebrekestelling is not required under the LAR in the same way as under the Dutch Awb, a written reminder can be useful. It records the applicant’s position and may help demonstrate that the applicant has acted reasonably.
Keep an eye on enforcement deadlines. If a court-ordered deadline is missed, the applicable period for requesting enforcement may be limited. A six-week period applies. Missing that period can have consequences for admissibility.
Consider interim relief where necessary. If waiting for the ordinary LAR procedure would cause serious or urgent problems, civil-court summary proceedings (kort geding) may provide an additional route to seek an order requiring the authority to decide, potentially combined with a penalty payment.
Conclusion
For anyone waiting for a permit, license, concession, objection decision or other governmental decision, the law provides protection against indefinite delay. Transparency and accountability in public administration are not only about access to information. They also require the government to communicate, decide and respect the legal deadlines that apply to them.
If you are facing a prolonged government delay, it is important to identify the applicable deadline and the remedy available in your particular case. Acting at the right time makes the difference between an unresolved application and an enforceable legal remedy.
_______________________________________________________________
BZSE law advises businesses and individuals in Curaçao and Sint Maarten on administrative law proceedings, permit applications and regulatory disputes. If you are facing delay on a pending application or decision, contact us via dkweekel@bzselaw.com or info@bzselaw.com.
Disclaimer: This blog provides general information and is not intended as legal advice. BZSE strongly recommends seeking personalized legal advice based on your specific circumstances before making any decisions or taking action.
More articles →
By Dana Kweekel | BZSE law | November 2026
You filed an application months ago — perhaps for a business permit, a concession, a building license, or a residency permit. The deadline has passed, emails go unanswered, and you are told to "be patient". What are your rights when the government does not decide within the applicable timeframe?
In Sint Maarten, administrative bodies such as the government or SZV regularly face delays in deciding on applications and objections. The reasons may include staff shortages, incomplete policy, pending studies, or internal reorganization. But recent case law makes one point clear: internal administrative problems do not remove the government's legal obligation to decide.
This article explains what happens when the government does not decide on time, what the courts have said about governmental delay, and which remedies are available to applicants.
The law
Administrative law in Sint Maarten is governed by the Landsverordening administratieve rechtspraak (National Ordinance on Administrative Law / "LAR"). Article 3, paragraph 3, provides the starting point:
"Where the statutory period for issuing a decision has expired without a decision being given, or — in the absence of such a period — where a decision has not been given within a reasonable time, this is deemed a refusal to give a decision."
In other words, where the applicable deadline has passed without a decision, the law treats the silence as a refusal to decide. That gives the applicant access to the legal remedies available against this refusal.
For decisions on objections (beslissingen op bezwaar), the statutory period is four months. This period may be extended once by thirty days, provided that prior notice is given.
For primary applications, such as permits, concessions and licenses, the applicable period may be set by sector-specific legislation. If no specific period applies, the authority must decide within a reasonable time. Courts have generally regarded around three months as a useful benchmark for straightforward matters, while more complex applications may require more time.
What the courts have said
Recent decisions of the Joint Court of Justice and the Courts of First Instance in the Dutch Caribbean show a consistent approach: administrative difficulties do not, by themselves, justify missing a statutory or reasonable decision deadline.
"We don't have enough staff." A 2026 Sint Maarten case illustrates this point. The Minister explained that a high workload and capacity shortages at the Legal Affairs department had prevented the processing of an objection filed eight months earlier. The Court nevertheless held that "capacity shortages do not relieve the respondent of its obligation to decide on the objection in time". The objection had not been processed during the statutory period.
"We need to develop policy first." The same approach was taken in the Otium case of 10 June 2026 , concerning an electricity production concession in Curaçao. The Minister argued that he first needed to develop an allocation mechanism and complete technical studies. The Court found that the Minister had essentially waited for an external consultant’s report and held that this passive approach had caused the court-ordered deadline to be missed.
"The legally required advisory committee doesn't exist." In a 2025 Bonaire pharmacy permit case , the Minister argued that he could not decide because the statutory advisory committee had not been established. The Court held that the absence of the committee did not relieve the Minister of his obligation to decide in time. If necessary, the Minister should have found another way to obtain the required expert advice.
"We're waiting for advice from another department." A 2026 Curaçao building permit case concerned a delay of more than two years while the Minister waited for an assessment from the fire department. The Court held that waiting for advice from another department did not relieve the Minister of the duty to monitor the decision deadline and decide in time. The Court emphasized the applicant’s interest in knowing where she stands within a reasonable period.
The "pokopoko" principle
The strict approach to decision deadlines may raise questions about the so-called pokopoko principle in Dutch Caribbean jurisprudence. Those questions deserve a careful answer, because the principle does not merely fail to support governmental delay — its underlying rationale directly confirms the opposite.
The term comes from Papiamento and means "little by little" or "slowly." The principle was first articulated by the Joint Court of Justice in 2001 and confirmed by the Dutch Supreme Court in Erven R./Sint Eustatius. That case concerned a decades-long series of assurances by functionaries of the Island Territory of Sint Eustatius about the transfer of a plot of land, made by an organ that lacked formal authority to bind the territory. When the territory ultimately refused to proceed, the heirs of the original claimant sought damages for breach of trust. The central question was how much legal weight could be attached to that informal conduct.
The Supreme Court's answer was grounded in the nature of small-island administration. It held that, in a small-scale community where personal relationships are important and an explicit refusal may not easily be given, the rules governing authority and formal decision-making must be strictly observed. This principle carries significant weight, even though the Court also held that, in exceptional circumstances, even unauthorized conduct can give rise to liability. The principle therefore defines the starting point: formal procedures must be followed, precisely because informal dealings are more likely and more dangerous in close-knit communities.
The Supreme Court confirmed this reasoning in October 2024 in Shipyard/Sint Maarten, where Shipyard argued that a building permit issued by the Minister of VROMI implied the government's private-law consent to deviate from the terms of its ground lease. The Court rejected that argument. Critically, it also set out the reason why formal procedures carry particular weight in this context: public administration on Sint Maarten is, as a rule, less well-staffed and equipped for all its tasks than in European Netherlands, and it is precisely for that reason that strict compliance with procedures is of great importance, to safeguard the interests of the territory and its population.
It might be argued that the same circumstances — limited administrative capacity and the small-island context — should lead courts to allow more time before a deemed refusal arises. The pokopoko principle, on this reading, would reflect a broader recognition that formal legal standards must accommodate local realities.
The case law does not support that argument. The pokopoko principle was developed in response to the risk of informal conduct in small communities, and the Supreme Court has been explicit that limited resources are a reason to insist on formal procedures, not to relax them. That conclusion follows directly from the principle's own logic: it concerns situations where a citizen relies on informal or unauthorized governmental conduct, whereas a decision deadline involves a citizen asking the government to comply with a statutory obligation it assumed when it accepted the request. Invoking the pokopoko principle to argue for more time would turn its rationale on its head.
The courts have therefore consistently emphasized legal certainty. Applicants must be able to know when a government decision can be expected and what legal options are available if it does not come. The particular circumstances of small-island administrations may be relevant in some areas of administrative law, but — as the Supreme Court has made clear — those circumstances make enforceable deadlines more, not less, important.
What you can do
The LAR provides several remedies when an authority does not decide on time. The appropriate step depends on the circumstances and on whether the authority has already been ordered by a court to decide.
Step 1 — Appeal against the deemed refusal. Once the applicable deadline has expired, an applicant can file an appeal (beroep instellen) with the Court of First Instance. The appeal period is six weeks from the date on which the decision is deemed to have been refused. An appeal filed too early or after the six-week period may be declared inadmissible.
tep 2 — The court orders the authority to decide. If the appeal is well-founded, the court can order the authority to issue a decision within a specified period. The period may vary depending on the nature and complexity of the matter.
Step 3 — Penalty payments for non-compliance. If the authority does not comply with the court’s order, the court may attach a penalty payment (dwangsom) under Articles 50 or 97/98 LAR. In the Otium electricity concession case, the Joint Court imposed a lump-sum penalty of Cg 1,000,000 for failure to meet the January 2027 deadline.
Step 4 — The court may decide itself. Article 50 LAR allows the court, in appropriate circumstances, to substitute its own decision for that of the authority. In a 2026 Curaçao building permit case, the Court concluded that the long passage of time and the Minister’s lack of decisiveness gave it insufficient confidence that the Minister would comply with another order. The Court therefore ordered the Minister to grant the building permit.
Step 5 — Damages. The Joint Court may award non-pecuniary damages for unreasonable procedural delay under Article 6 of the European Convention on Human Rights. The current rate referred to in the case law is Cg. 500 per half-year of delay. Material damages, such as lost income or missed opportunities, may be pursued separately where the legal requirements for such a claim are met.
Practical guidance
Keep track of your deadlines. Record when your application or objection was filed, which statutory or reasonable decision period applies, and when the decision is deemed to have been refused. These dates determine when legal remedies become available.
Do not act too early, but do not wait indefinitely. An appeal filed before the reasonable decision period has expired will be inadmissible. For straightforward matters, three months is a useful benchmark. More complex applications may justify a longer period, but the authority should be actively dealing with the application rather than simply allowing it to remain pending.
Put the authority on notice. Although a formal ingebrekestelling is not required under the LAR in the same way as under the Dutch Awb, a written reminder can be useful. It records the applicant’s position and may help demonstrate that the applicant has acted reasonably.
Keep an eye on enforcement deadlines. If a court-ordered deadline is missed, the applicable period for requesting enforcement may be limited. A six-week period applies. Missing that period can have consequences for admissibility.
Consider interim relief where necessary. If waiting for the ordinary LAR procedure would cause serious or urgent problems, civil-court summary proceedings (kort geding) may provide an additional route to seek an order requiring the authority to decide, potentially combined with a penalty payment.
Conclusion
For anyone waiting for a permit, license, concession, objection decision or other governmental decision, the law provides protection against indefinite delay. Transparency and accountability in public administration are not only about access to information. They also require the government to communicate, decide and respect the legal deadlines that apply to them.
If you are facing a prolonged government delay, it is important to identify the applicable deadline and the remedy available in your particular case. Acting at the right time makes the difference between an unresolved application and an enforceable legal remedy.
_______________________________________________________________
BZSE law advises businesses and individuals in Curaçao and Sint Maarten on administrative law proceedings, permit applications and regulatory disputes. If you are facing delay on a pending application or decision, contact us via dkweekel@bzselaw.com or info@bzselaw.com.
Disclaimer: This blog provides general information and is not intended as legal advice. BZSE strongly recommends seeking personalized legal advice based on your specific circumstances before making any decisions or taking action.